Schloss-Röttgen-Tunnel
Railway tunnel in Cologne-Eil whose planned length grew from 400 to 1,047 m in stages, most recently amid a legal dispute over the Röttgen stud farm.
The tunnel takes its name from Schloss Röttgen and the Röttgen stud farm, both of which it passes beneath. It protects the local landscape as well as the stud's facilities and the pastures and paddocks in front of them.
Source: Wikipedia
At a Glance
- Type
- Railway tunnel on the Cologne Airport Loop
- Location
- Cologne-Eil, Porz district
- Length
- 1,047 m
- Tracks
- Two, with a maximum speed of 130 km/h
- Construction
- Closed box frame along its entire length
- Opened
- 12 June 2004
Because the Röttgen stud farm feared that railway noise would harm its horse breeding, the tunnel was extended from an originally planned 400 metres to 1,047 metres – costing an extra 7.7 million euros and causing a delay of about 18 months that kept the airport loop from being finished in time for the opening of the high-speed line in 2002.
Planning in Stages
In early 1992, the plans for this section did not yet include a tunnel. By late 1995, a 400-metre structure was envisaged. During the planning approval procedure, for which the documents were submitted in 1996, an extension was added. In mid-1999 and early 2000, the planned length stood at 517 metres each time.
The Legal Dispute over the Stud Farm
The operators of the Röttgen stud farm sued to stop the project. Their concern was that the noise of trains on the planned airport loop could harm breeding success. In spring 1999, the Higher Administrative Court of Münster provisionally rejected a demanded construction freeze after a summary review, because the lawsuit was unlikely to succeed. After more than a year of dispute, the court followed an expert opinion by the lawyer and dressage rider Reiner Klimke. He took the view that horses quickly get used to the sound of passing trains. The feared tunnel boom never occurred.
Compromise and Extension
In the end, the state of North Rhine-Westphalia and the Mehl-Mühlen-Stiftung agreed on a compromise: the tunnel was extended by 530 metres to 1,047 metres. Once the plans had been amended accordingly, the foundation withdrew the last of its three lawsuits before the Higher Administrative Court. As a result, the planning approval took effect on 2 February 2001. The direct additional costs amount to 7.7 million euros.
Construction and Operation
Preparatory work began in February 2000, with open-cut construction initially planned. Privacy fences were meant to shield the breeding operation from disturbance. To reduce the impact of the construction site, the tunnel was built in sections. According to Deutsche Bahn, the negotiations with the stud farm delayed construction by around 18 months, so the loop was not ready when the high-speed line opened in 2002. Since opening together with the airport loop, long-distance, regional and S-Bahn trains have run through the tunnel.
Timeline
- 1996Planning approval documents submitted
- 1998Planning approval decision issued in first half of year
- 1999Higher Administrative Court Münster provisionally rejects construction halt
- Februar 2000Preparatory construction work begins
- 2. Februar 2001Planning decision becomes effective with extension to 1,047 m
- 12. Juni 2004Opened together with the airport loop
Map
Blue dots: other places nearby — tap to explore.
You might also like — related or nearby
Comments
- Loading comments…
Sources & links
Auto-generated, last verified: 2026-11-08
How this page is made
This page draws on open sources — Wikipedia, Wikidata, official websites and the city’s open data — plus basic place data and photos from Google Maps where a place is listed there. Every statement is checked against the sources linked here, and pages are refreshed regularly.
Spotted a mistake anyway? Tell us below — we read every submission.